Week 3 Construction Update

The soil engineer found the soil to be good for building at the start of the week.  So, footing excavation took place on Thursday.  Then, the footings were poured on Friday.  The construction crew braved frigid temperatures from the polar vortex and a dusting of snow.  It was a little concerning to hear one of the guys say the footing plans were a bit confusing in one section.  Hopefully, they got it right.  The next task is to remove the soil from the trenches that were dug for the footings. 

Footings - Excavation1.jpeg
Footings - Excavation2.jpeg
Footings - Concrete Truck.jpeg
Footings - Concrete.jpeg