Tile, Flooring, and Interior Paint

Tile, flooring, and interior paint selections have been made. 

Tile selections include the following:

  • Grey hex on bathroom floors with iron colored grout: Spearteck Buckhead Collection; BHGY1 HexMat; Grout: Maipei 107 Iron

  • Long, white subway tiles in showers with iron colored grout : Florida Tile, 310, 4 x 16 Arctic Streamline, Gloss; Grout: Maipei 107 Iron

  • Kitchen backsplash and rec area / bar wall in inverted, white subway tiles with iron colored grout: MSI White Glossy Inverted 3 x 6; Beveled; Grout: Maipei 107 Iron

  • Laundry room in slate porcelain tile with matching grout: 12 x 24 Formations Flint

Hardwood floors will be a white oak with natural knots, markings and variations in grain and color to give the space real character.  An engineered product will be used on the first floor because of the slab construction, and solid hardwoods will be used on the second and third floors.  Somerset, the company that makes the floor, manufactures the product in the United States from domestically grown and harvested Appalachian hardwood.  The material conforms to Appalachian Hardwood Manufacturers, Inc.’s Verified Sustainable Seal.  Go here for the product information page.

The interior paint colors will be Sherwin Williams Extra White (SW 7006) and Repose Gray (SW 7015).  Kitchen and bar cabinets, trim, and ceilings will be in white while the walls will be gray.

Tile 01.jpg
Floor 01.jpg
Paint 01.jpg

Week 27 Construction Update

Since the last update, several construction milestones have been achieved.  These include completion of framing, installation of roof membrane, construction and installation of indoor staircases, and installation of exterior door hardware.  Apparently, the staircases were heavy and long.  HVAC work begins this week.

Framing 31.JPG
Stairs 01.JPG
Stairs 02.JPG
Stairs 03.JPG
Stairs 04.JPG
Stairs 05.JPG
Roof 02.JPG
Door 01.JPG
Door 02.JPG
HVAC 01.jpg

Week 17 Construction Update - Call in the (Steel) Reinforcements!

Building has been stalled for about 5 weeks because of an engineering problem. The original plans called for 2x10's over a large span between floors. The builder flagged that this would not be structurally sound, so the builder, architect, and a new engineer collaborated on an update to the framing plan. The update called for several steel beams to be installed between floors. So, the LVL construction is now complemented by steel beams. The builder joked that the house could double as a bomb shelter. I probably wouldn't go that far, but it should definitely withstand the quakes in the Central Virginia Seismic Zone, including the 5.8 magnitude quake that struck in 2011.

After the framing plan was re-engineered, additional materials, like the steel beams, were ordered. The framing crew returned to the job on May 8, and they should be complete in the next few weeks.

Steel Beams 02.jpeg
Steel Beams 01.jpeg
Steel Beams 03.jpeg

Week 10/11 Construction Update - We've Got Wood

Wood was delivered on Wednesday, March 20, and framing started the next day. It’s starting to look like a house. The framing uses a fair amount of laminated veneer lumber (LVL). According to Wikipedia, LVL is an engineered wood product that uses multiple layers of thin wood assembled with adhesives. It is typically used for headers, beams, rimboard, and edge-forming material. LVL offers several advantages over typical milled lumber: Made in a factory under controlled specifications, it is stronger, straighter, and more uniform. Due to its composite nature, it is much less likely than conventional lumber to warp, twist, bow, or shrink.

Framing 01.jpeg
Framing 03.jpeg
Framing 04.jpeg
Framing 05.jpeg
Framing 06.jpeg
Framing 07.jpeg
Framing 08.jpeg
Framing 09.jpeg

Week 8 Construction Update

This week saw backfill rock around the foundation walls, both inside and outside. Ground works plumbing was completed as well. After waterproofing was finished, the City conducted the foundation inspection, which passed. The slab is now ready to be poured. Prior to pouring, the City conducts a slab inspection. The original plans show a drain in the garage floor, but after conferring with the construction manager, we decided to slope the garage towards the driveway as an effective but less costly way to address any water. Unfortunately, the City failed the slab inspection since the drain wasn’t present. So, the construction manager will red line the plans, have it re-inspected, and hopefully have the concrete truck out next week.

In other news, the house next door may have gone into foreclosure. A neighbor mentioned this, and then I found foreclosure announcements for the property in the 02/21/2018 and 070/4/2018 editions of Style Weekly. Though, there isn’t anything more recent that I found. I’ll have to monitor to see what happens. I do know that the tenants of the property moved out a few months ago. Just before that happened, the owner of the property called me to ask if either (1) I would be interested in buying his house or (2) I’d be interested in selling him my land so that he could combine it with his as a house and lot for sale. Obviously, I declined both offers.

Foundation Walls - 10.jpeg
Foundation Walls - 11.jpeg
Foundation Walls - 12.jpeg
Foundation Walls - 13.jpeg
Foundation Walls - 14.jpeg
Foundation Walls - 15.jpeg

Week 6 Construction Update

An engineer issued the foundation certification, and the surveyor completed the foundation survey.  A concrete truck arrived and pumped in the foundation walls.  Pre-work for plumbing is complete.  The builder took the first draw, representing 11.58% of the budget.  Next up, the city should inspect the foundation, and then the dirt around the foundation can be backfilled.

Foundation - Walls 8.jpeg

Week 4 Construction Update

The spoils (extra dirt) from the footings were removed this week.  The foundation was pinned.  And, the bricks and blocks for the foundation arrived on site.

Funny, not funny family story… When my parents built their custom home in Texas in the early 1990’s, our family was still living in Florida until the house was finished. My mom picked out a solid red brick for the house but was not able to be on site to look at them when they arrived. My dad, who’s colorblind, took a photo like the one below of the bricks on the site. They looked a bit orange in the photo, and my mom asked about that when she saw the photograph. My dad said those must be for the house next door and that the nearby pile of red bricks was for their house. My mom’s next photo update of the house occurred when the masonry was complete. That picture showed orange and black bricks on the house. Turns out the wrong bricks were ordered and the red bricks were for the house next door. My mom hated those orange bricks on her house her entire life.

Foundation Pin.jpeg
Foundation Blocks and Bricks.jpeg